Most foreign investors into India discover FEMA reporting after the deadline, not before it. The money arrives, the shares are allotted, and nobody realises that two regulators are now counting the same thirty days. The forms themselves are short. What costs money is the arithmetic โ which event starts the clock, which party has to file, and the three-year line beyond which a late filing stops being a fee and becomes a contravention. Below is the current position, taken from the Reserve Bank’s own regulations and circulars rather than from memory.
What FEMA Reporting Is, and Who Actually Has to File It

FEMA reporting is the set of filings an Indian entity must make to the Reserve Bank of India, through its authorised dealer bank, every time foreign money enters or leaves its capital structure. The obligation sits on the Indian company or LLP โ not on the foreign investor who sent the money, and not on the investor’s lawyers abroad.
That allocation of responsibility is the first thing that goes wrong with FEMA reporting. A fund wires subscription money, the Indian subsidiary’s finance team treats the receipt as a routine credit, and nobody tells them a clock started the day the funds hit the account. The investor assumes the company is handling it. The company assumes the investor’s advisers are. Three months later the position is already a contravention.
Filings are made on the Single Master Form in the Reserve Bank’s FIRMS application, which consolidated what used to be a scattered set of returns. Under A.P. (DIR Series) Circular No. 22 of 4 January 2023, forms submitted on the portal are auto-acknowledged and the authorised dealer bank then verifies them within five working days against the uploaded documents. An auto-acknowledgement is not approval โ it is a receipt.
The First Clock Starts the Day the Money Lands
Before any FEMA reporting falls due, there is a deadline most people do not know exists. Under the Foreign Exchange Management (Mode of Payment and Reporting of Non-Debt Instruments) Regulations, 2019 โ Notification No. FEMA 395/2019-RB โ equity instruments must be issued to the foreign investor within sixty days from the date of receipt of the consideration.
If they are not issued in that window, the regulation does not simply leave the money sitting there. It must be refunded to the investor โwithin fifteen days from the date of completion of sixty daysโ, by outward remittance through banking channels or by credit to the investor’s repatriable foreign currency or Rupee account.
Read those two periods together and the practical consequence is stark: a board that is still arguing about valuation on day fifty-five has a legal obligation to send the money back, not an option to hold it. The regulation also fixes how the consideration may arrive in the first place โ as an inward remittance through banking channels, or out of funds held in a repatriable foreign currency or Rupee account maintained under the Deposit Regulations.
This is why the sequencing of a round matters more in India than the paperwork itself. Valuation, board and shareholder approvals, and the share allotment itself all have to fit inside sixty days of the wire, and only then does the reporting clock begin.
Form FC-GPR: Thirty Days From Issue, Not From Receipt
Form FC-GPR is the central FEMA reporting filing. Regulation 4(1) of FEMA 395 requires an Indian company issuing equity instruments to a person resident outside India, where the issue is reckoned as foreign direct investment, to โreport such issue in Form FC-GPR, not later than thirty days from the date of issue of equity instrumentsโ.
The trigger is the issue โ the allotment โ not the receipt of funds. That distinction is the single most common source of miscalculated deadlines. A company that receives money on 1 March and allots on 20 April has an FC-GPR due by 20 May, not by 31 March. A company that allots on the day the money arrives has thirty days from that day, and the two clocks collapse into one.
Since the Reserve Bank moved reporting onto the Single Master Form, the old two-step process โ an Advance Reporting Form on receipt, then FC-GPR on allotment โ no longer applies. The Entity Master module and the integrated form structure were introduced by A.P. (DIR Series) Circular No. 30 of 7 June 2018, and the advance reporting step was folded into a single revised FC-GPR.
One practical prerequisite follows from that architecture. An entity that has received, or expects to receive, foreign investment has to be registered on FIRMS with its Entity Master before it can file any transactional form. Discovering that on day twenty-eight of a thirty-day window is a bad day.
Form FC-TRS: Sixty Days, and the Earlier of Two Events

Form FC-TRS covers transfers rather than issues โ secondary sales between a resident and a non-resident, and transfers between non-residents holding on repatriable and non-repatriable bases. Regulation 4(3) requires it to be filed within sixty days of the transfer of equity instruments or of the receipt or remittance of funds, whichever is earlier.
โWhichever is earlierโ does the damage. In a deal where consideration is paid at signing and shares move at completion weeks later, the clock runs from the payment, not the share transfer. In a deal structured the other way round, it runs from the transfer. Secondary purchases of Indian shares are routinely reported late for exactly this reason: the parties diarise the closing date and the money moved first.
Responsibility for the FEMA reporting also shifts depending on who is resident. For a transfer between a resident and a non-resident, the filing is made by the resident party or the non-resident acquiring on a repatriable basis; a transfer on a recognised stock exchange by a person resident outside India is reported by that person. On an exit, a seller who has already left the deal has little incentive to chase a form โ which is why the obligation belongs in the share purchase agreement, with evidence of filing as a condition.
The Other Forms, and the Clock Each One Starts
FC-GPR and FC-TRS are not the whole of FEMA reporting. FEMA 395 sets a separate form and period for each kind of event, and a foreign-owned group will typically trip over at least two of these in its first two years:
- Form ESOP โ an Indian company issuing employees’ stock options to a person resident outside India files within 30 days from the date of issue (Regulation 4(4)).
- Form LLP(I) โ an LLP receiving foreign capital contribution or profit share files within 30 days of receipt (Regulation 4(6)).
- Form LLP(II) โ disinvestment or transfer of capital contribution between a resident and a non-resident, within 60 days of receipt of funds (Regulation 4(7)).
- Form InVi โ an investment vehicle issuing units to a person resident outside India, within 30 days of issue (Regulation 4(10)).
- Form DI โ indirect foreign investment: an Indian company making a downstream investment reports within 30 days from the date of allotment (Regulation 4(11)).
- Form CN โ a start-up issuing convertible notes to a person resident outside India, within 30 days of issue, with transfers also reportable within 30 days (Regulation 4(12)).
Two patterns are worth internalising. Issues are generally thirty days; transfers and disinvestments are generally sixty. And a downstream investment by your own Indian subsidiary into another Indian company is a reportable event in its own right โ groups that build a two-tier Indian structure after entry often miss Form DI entirely, because no foreign money moved at that step.
Form FLA: The Annual Return Nobody Diarises
Every entity that has received foreign direct investment, or made direct investment abroad, must file the annual return on Foreign Liabilities and Assets. Regulation 4(2) of FEMA 395 requires Form FLA to be submitted โon or before the 15th day of July of each yearโ, and the Reserve Bank’s FLA guidance confirms the same date and the filing route.
Four features catch people out. It is filed on the FLAIR portal, not on FIRMS. It covers the position as at 31 March for the previous and current financial years, so the first return can fall due on figures that are barely final. It may be filed on provisional or unaudited accounts within the due date โ but once audited accounts are ready, the entity must request permission to submit a revised return. And limited liability partnerships are squarely within scope, which surprises LLPs that have never filed anything with the Reserve Bank before.
Form FLA is the FEMA reporting that most often reveals a historical problem. A new adviser sits down to prepare it, reconciles the foreign holding, and discovers an FC-GPR from three years ago that was never filed.
Two Regulators, One Event: the MCA Clock Runs in Parallel

A share issue to a foreign investor triggers company-law reporting as well as FEMA reporting, and the two are administered by different authorities with different portals and different consequences. Rule 12(1) of the Companies (Prospectus and Allotment of Securities) Rules, 2014, read with section 39(4) of the Companies Act, 2013, requires a company making any allotment of securities to file a return of allotment in Form PAS-3 with the Registrar of Companies within thirty days of the allotment.
So a single allotment to an overseas parent sets two thirty-day clocks running from the same date โ PAS-3 to the Ministry of Corporate Affairs, FC-GPR to the Reserve Bank through the authorised dealer bank. They are not alternatives, and filing one does not evidence the other. The documents also differ: FC-GPR work turns on the valuation certificate, the inward remittance advice and the investor’s KYC, while PAS-3 turns on the allottee list and the board and shareholder resolutions.
Groups that outsource company secretarial work and exchange-control work to different providers should be explicit about which provider owns which clock. In our experience that single line in an engagement letter prevents more late filings than any calendar.
Pricing and Valuation: Why Filings Get Sent Back
FEMA reporting filed on time can still fail, because the authorised dealer bank verifies it against documents and against the pricing rules. The Reserve Bank’s Master Direction on Foreign Investment in India sets the floor for an issue of equity instruments by an unlisted Indian company: not less than โthe valuation of equity instruments done as per any internationally accepted pricing methodology for valuation on an arm’s length basis duly certified by a Chartered Accountant or a SEBI registered Merchant Banker or a practicing Cost Accountantโ.
The same logic applies in both directions on a transfer. A transfer to a person resident outside India may not be priced below that certified valuation; a transfer from a non-resident to a resident may not be priced above it. The rule is a one-way ratchet in each case, designed to stop value leaking out of or into India through the price.
Two consequences for planning. First, the valuation certificate is not a formality to be produced after the fact โ it conditions the price, so it belongs before the term sheet hardens. Second, the pricing guidelines do not apply to investment made on a non-repatriation basis, which is one of the genuine structural differences between repatriable foreign investment and investment by non-residents on a non-repatriable footing.
Missing a Deadline: What the Late Submission Fee Fixes
Late FEMA reporting is not automatically a dead end. Under A.P. (DIR Series) Circular No. 16 of 30 September 2022, a delay can be regularised by paying a late submission fee, computed by the portal and advised by the authorised dealer bank. The circular sets two tiers:
- A flat โน7,500 for the annual and periodical filings โ Form FLA, FCGPR(B), Form ODI Part-II/APR, Form OPI, evidence of investment and other periodical reporting.
- For transactional reporting โ FC-GPR, FC-TRS, Form ESOP, Form LLP(I), Form LLP(II), Form CN, Form DI, Form InVi and the overseas-investment and borrowing forms โ โน7,500 + (0.025% ร A ร n), where A is the amount involved in the delayed reporting and n is the delay rounded upwards to the nearest month.
The fee is capped at 100 per cent of A and rounded upwards to the nearest hundred. On a small delay the arithmetic is trivial; on a large round reported a year late it is not, because the amount involved drives the whole calculation.
The limit that matters is temporal. The late submission fee facility is available up to three years from the due date of the reporting. Beyond three years it cannot be accepted, and the circular is explicit that a person who neither files in time nor files with the fee is liable to penal action under FEMA. The 2023 rationalisation circular reflects the same fork: on a delayed filing the bank either advises the late submission fee or advises compounding.
Beyond Three Years: Compounding Unreported FEMA Reporting
Once the three-year window has closed, the route is compounding โ an application to the Reserve Bank to settle the contravention. The Master Direction on Compounding of Contraventions under FEMA, 1999 governs the process, and section 15 of the Act allows a contravention to be compounded โwithin one hundred and eighty days from the date of receipt of applicationโ by Reserve Bank officers.
The exposure being settled is set by section 13(1): a penalty of up to thrice the sum involved where the amount is quantifiable, up to โน2 lakh where it is not, and for a continuing contravention a further penalty of up to โน5,000 for every day after the first day during which the contravention continues. Compounding settles at a fraction of the statutory maximum in practice, but the maximum is what sits in the diligence memo of whoever buys the company next.
Two procedural points are worth knowing. Compounding powers have been delegated to Reserve Bank regional and sub-offices, so the application does not necessarily travel to Mumbai. And the former practice of treating some reporting breaches as merely โtechnicalโ contraventions, which attracted an administrative warning rather than a penalty, was discontinued in November 2020. An unreported allotment is a contravention, not an irregularity.
A FEMA Reporting Calendar You Can Actually Hold
Reduced to the discipline a finance team can run without specialist help, FEMA reporting for a foreign-owned Indian entity comes down to a short list of event triggers and one annual date:
- Money received โ allot within 60 days, or refund within 15 days of that period ending.
- Shares allotted โ FC-GPR within 30 days to the Reserve Bank, PAS-3 within 30 days to the Registrar of Companies.
- Shares transferred โ FC-TRS within 60 days of transfer or of money moving, whichever is earlier.
- Options granted, notes issued, units issued โ Form ESOP, Form CN or Form InVi within 30 days.
- Your Indian company invests in another Indian company โ Form DI within 30 days of allotment.
- Every year โ Form FLA on the FLAIR portal by 15 July, revised once audited accounts are ready.
- Before any of it โ Entity Master registered on FIRMS, and a valuation certificate that supports the price.
None of these is difficult. They are missed because they are owned by nobody: the investor thinks the company files, the company thinks the bank files, and the bank only verifies what it is given. Assigning each trigger to a named person, with the authorised dealer bank relationship documented, is most of the work.
The consolidated source for the operational detail is the Reserve Bank’s Master Direction on Reporting under FEMA, 1999, which is reissued rather than track-changed and was last updated on 1 October 2026. Check the current version before you rely on any filing period โ including the ones in this article.
How PerspireIP Can Help
PerspireIP runs reporting calendars for foreign-owned Indian entities as part of India entry, due diligence and compliance work โ mapping each event trigger to a form and an owner, assembling the documents the authorised dealer bank will verify, and reconstructing the position where filings were missed before a buyer or an auditor finds them. If you are planning a round, an acquisition or a clean-up of an entity you already own, tell us what has happened so far and we will scope the work and quote before anything starts.
Related reading: choosing between a subsidiary, LLP, branch and liaison office decides which of these forms you will ever file; permanent establishment risk turns on how you operate once you are there; and financial due diligence on an Indian target is where unreported allotments usually surface.
This article describes professional services and is general information, not legal, tax or investment advice. Indian entry routes, sectoral caps, filing deadlines and thresholds change with each Finance Act and RBI circular, and the right answer depends on your sector and facts. We confirm the current position for your situation before any filing is made or any transaction is completed.
Frequently Asked Questions
Who is responsible for FEMA reporting โ the Indian company or the foreign investor?
The Indian entity receiving the investment owns the FEMA reporting and files the forms, through its authorised dealer bank, on the Reserve Bank’s FIRMS portal. The foreign investor has no filing portal of its own. On a transfer of shares the obligation falls on the resident party or on the non-resident acquiring on a repatriable basis, which is why share purchase agreements should make evidence of filing a contractual condition rather than an assumption.
When is Form FC-GPR due?
Not later than thirty days from the date of issue of the equity instruments. Regulation 4(1) of the Foreign Exchange Management (Mode of Payment and Reporting of Non-Debt Instruments) Regulations, 2019 ties the period to the issue โ the allotment โ and not to the date the subscription money was received, so a company that receives funds and allots several weeks later counts the thirty days from allotment.
When is Form FC-TRS due?
Within sixty days of the transfer of the equity instruments or of the receipt or remittance of funds, whichever is earlier. Because the earlier event controls, consideration paid at signing starts the clock even if the shares do not move until completion weeks later.
What happens if shares are not issued within sixty days of receiving the money?
The consideration must be refunded to the investor within fifteen days from the date the sixty-day period ends, by outward remittance through banking channels or by credit to the investor’s repatriable foreign currency or Rupee account. It is an obligation, not an option, so valuation and approvals have to fit inside the sixty days.
Can a late FEMA reporting filing be fixed by paying a fee?
Yes, within limits. A.P. (DIR Series) Circular No. 16 of 30 September 2022 allows a late submission fee: a flat โน7,500 for annual and periodical filings such as Form FLA, and โน7,500 plus 0.025 per cent of the amount involved per month of delay for transactional forms such as FC-GPR and FC-TRS, capped at 100 per cent of that amount. The facility is available only up to three years from the due date; after that the route is compounding.
Who has to file Form FLA, and by when?
Any entity that has received foreign direct investment or made direct investment abroad, including a limited liability partnership, must file the annual Foreign Liabilities and Assets return by 15 July each year on the Reserve Bank’s FLAIR portal. It may be filed on provisional figures within the due date, but a revised return must then be submitted once audited accounts are available.
Does a share allotment to a foreign parent need both an MCA and an RBI filing?
Yes. The same allotment requires Form PAS-3 with the Registrar of Companies within thirty days under Rule 12(1) of the Companies (Prospectus and Allotment of Securities) Rules, 2014, and Form FC-GPR with the Reserve Bank within thirty days. The two run in parallel from the same date and filing one does not satisfy the other.
What is the penalty for not reporting foreign investment at all?
Section 13(1) of FEMA, 1999 provides for a penalty of up to three times the sum involved where the amount is quantifiable, up to โน2 lakh where it is not, and a further penalty of up to โน5,000 for each day a contravention continues after the first day. For FEMA reporting breaches, Reserve Bank practice since November 2020 no longer treats reporting breaches as merely technical contraventions attracting a warning.